In an effort to address anticipated electricity shortages and reliability challenges in California, the California Public Utilities Commission (CPUC) voted on November 7 to authorize the procurement of 3,300 MW of energy by 2023.
FERC Staff issued an October 4 report on Commission-led critical infrastructure protection (CIP) reliability audits completed during fiscal year 2019. The report provides lessons learned and identifies voluntary practices that FERC Staff observed during those audits that could improve the protection of electric infrastructure from cyberattacks.
For the first time, FERC has found that significant investments in an existing licensed hydroelectric facility by a licensee will be considered when establishing the license term in a relicensing proceeding, potentially aiding the licensee in obtaining a longer license term.
Facing what it deems an “unprecedented number of FOIA requests” for nonpublic information related to utility violations of the North American Electric Reliability Corporation (NERC) critical infrastructure protection (CIP) requirements governing cybersecurity compliance for critical electric infrastructure, FERC Staff has issued a white paper proposing to make publicly available additional information regarding those violations, including the names of the utilities involved.
FERC recently approved proposed Reliability Standard CIP-008-6, which expands the mandatory reporting requirements for Cyber Security Incidents that attempt to compromise the operation of the bulk power system.
New Jersey advanced several of the Murphy administration’s clean energy goals during June 2019. Over the past month, the state released a draft of its revised Energy Master Plan (EMP), approved the Ocean Wind offshore wind project proposed by Ørsted, and released a detailed analysis on energy storage development in New Jersey.
Consolidated Edison Company of New York, Inc. (Con Edison) and Orange and Rockland Utilities, Inc. (O&R) issued a draft joint Request for Proposals (RFP) on May 31 to competitively procure scheduling and dispatch rights from new energy storage projects.
The supply chain risks facing electric utilities have long been a concern for industry stakeholders and regulators alike. Reflecting those concerns, NERC submitted a report on May 28 to FERC recommending the expansion of requirements addressing supply chain cybersecurity risks for electric utilities, concluding that the scope of those requirements needed to expand to match the scope of the cybersecurity risk.
FERC Staff issued a report on March 29 on Commission-led critical infrastructure protection (CIP) reliability audits completed for fiscal years 2016 through 2018. The report provides lessons learned from those audits, as well as voluntary recommendations on cybersecurity practices to enhance the protection of electric infrastructure from cyberattacks.