The North American Electric Reliability Corporation (NERC)—the federally designated grid reliability regulator—has proposed expanding its oversight that could subject data centers to reliability requirements for the first time. Under an October 2026 petition filed with the Federal Energy Regulatory Commission (FERC), NERC would establish two new registration categories: Computational Load Owner (CLO) and Computational Load Operator (CLOP). For data center developers, owners, and operators, the proposal introduces a new layer of regulatory compliance into project planning, design, and ongoing operations.
The proposal reflects growing regulatory concern that large data centers, particularly those supporting AI and other computationally intensive activities, can experience sudden and substantial changes in electricity demand that threaten electric grid stability.
The proposed requirements would apply to data center sites with at least 50 megawatts (MW) of total connected load supplied through equipment connected to the bulk-power system at 100 kilovolts (kV) or higher. Importantly, the 50 MW threshold includes cooling and other supporting infrastructure, not just computing equipment.
The triggering criteria apply to NERC’s proposed definition of a Computational Load Site, which may encompass multiple buildings and installations at a single location, potentially extending beyond individual property boundaries. As a result, developers will need to carefully assess campus configurations, electrical interconnections, and anticipated load growth to determine whether projects fall within the proposed registration framework.
Phased developments and campus expansions could trigger registration obligations even where individual buildings do not independently meet the 50 MW threshold. Data center developers, owners, and operators should begin considering the potential implications for site planning, infrastructure design, expansion strategies, and investment decisions, particularly for hyperscale and multi-building data center campuses.
The proposal also has potentially significant implications for data center leasing, ownership structures, financing, and commercial agreements. Because ownership and operational responsibilities are frequently divided among developers, landlords, tenants, and third-party operators, multiple parties at a single site could qualify for NERC registration. Commercial agreements may therefore need to expressly allocate registration responsibilities, compliance costs, operational obligations, and risks associated with future regulatory changes.
Developers and investors should also evaluate whether existing agreements adequately address potential modifications to facility operations, monitoring equipment, and security requirements. Although the current petition does not itself establish new Reliability Standards, NERC has separately adopted proposed standards addressing interconnection and modeling, operational data and communications, and protection coordination and disturbance monitoring. Future obligations could also potentially extend to cybersecurity and physical security requirements under NERC’s Critical Infrastructure Protection framework, increasing compliance costs and operational complexity.
The immediate priority for the data center industry is to evaluate potential regulatory exposure before the proposed framework becomes mandatory. Both the registration changes and new associated Reliability Standards remain subject to FERC approval, and implementation would occur according to approved schedules.
If new Reliability Standards applicable to data centers under the CLO and/or CLOP registrations are approved, compliance requirements would generally be phased in over approximately one year, with additional time for certain equipment installations. Nevertheless, developers, owners, operators, and investors should begin assessing existing facilities and development pipelines, identifying potentially covered sites, and incorporating regulatory risk allocation into new transactions and commercial arrangements.
Early engagement may help avoid costly redesigns, contractual disputes, or operational disruptions as NERC moves toward direct oversight of large data centers. NERC’s proposal also presents an immediate opportunity for industry participation, with comments due November 20, 2026, in FERC Docket No. RR27-1-000.
How We Can Help
Morgan Lewis routinely counsels clients on NERC registration, compliance programs, audit preparation, and enforcement, and advises on the development and commercial arrangements needed to support large load projects. In addition, the Morgan Lewis Data Center Strategic Initiative brings together lawyers across disciplines to address the increasingly interconnected issues involved in developing, financing, investing in, and operating data centers and digital infrastructure.
The firm’s multidisciplinary team advises participants across the data center lifecycle, including on-site acquisition and development, construction and leasing, power procurement and energy infrastructure, project and structured finance, investments and joint ventures, network connectivity, equipment and technology procurement, supply chain matters, tax and economic incentives, regulatory compliance, data center operations, and compute capacity arrangements.