On July 7, the US Court of Appeals for the District of Columbia Circuit issued its opinion in NRG Power v. FERC, vacating in part and remanding a May 2013 order by the Federal Energy Regulatory Commission (FERC) that had accepted PJM Interconnection, L.L.C.’s (PJM’s) revisions to the Minimum Offer Price Rule (MOPR) in the PJM electricity capacity market subject to PJM’s acceptance of certain modifications.
Earlier this month, the US Supreme Court issued a ruling that imposed a five-year statute of limitations period in which disgorgement could be ordered by an administrative agency penalizing regulatory violations.
On April 14, the US Court of Appeals for the DC Circuit issued its opinion in Emera Maine v. FERC, vacating and remanding FERC’s Opinion No. 531 in which FERC established a just and reasonable rate of return on equity (ROE) for transmission-owning utilities in the Northeast (NETOs) and adopted a new methodology for determining the ROE for FERC-jurisdictional electric utilities.
April 12, 2016 12:00 PM - 02:00 PM ET 11:00 AM - 01:00 PM CT 09:00 AM - 11:00 AM PT Event Location One Market, Spear Street Tower San Francisco, CA 94105-1596 United States We are proud to host the Energy Bar Association’s EBA Energizer: Mediating an Energy Case, in which panelists will discuss practical advice and mediation techniques.
The 5-4 decision temporarily blocks further execution of the EPA’s new plan to cut carbon emissions from existing power plants.
The D.C. Circuit concluded that sovereign immunity prevents FERC and NERC from imposing monetary penalties on federal agencies that violate Reliability Standards.
On August 15, the U.S. Court of Appeals for the District of Columbia Circuit rejected the challenges filed By various utilities, industry groups, and state commissions that claimed that the Federal Energy Regulatory Commission (FERC or the Commission) overstepped its authority.
In an order issued on March 30, [1] the Federal Energy Regulatory Commission (FERC or Commission) issued an order requiring "postage stamp" pricing to allocate the costs of new 500 kV and above transmission projects in the PJM Regional Transmission Organization Region.

On January 7, 2011, the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) in Murray Energy Corp. v. FERC, No. 09-1207 (D.C. Cir. Jan. 7, 2011), denied a petition for review By Murray Energy Corporation (Murray) of Federal Energy Regulatory Commission (FERC) orders authorizing construction of Rockies Express Pipeline LLC’s (REX’s) REX-East pipeline. The court rejected arguments concerning agency delegation of authority, fulfillment of certificate conditions, and consideration of safety issues.